Venue: Committee Room 2, Civic Centre, Oystermouth Road, Swansea
No. | Item |
---|---|
Minutes of the Meeting held on 31 January, 2019 PDF 116 KB Minutes: The
Minutes of the meeting held on 31 January, 2019 were approved as an accurate
record. |
|
Chairman's Letter to Councillor R.Stewart PDF 445 KB Minutes: The
contents of the Chairman’s letter to the Chairman of the Joint Committee dated
15 February, 2019, were noted. |
|
Minutes: Members
received a presentation by the Economic Development Manager It
was noted that the 11 agreed projects were at different stages, with three
projects having gone through the process and were awaiting United Kingdom and
Welsh Governments’ (UK/WG) approval. The
criteria for approval was in line with the green book of H.M.Treasury
and Members were advised that experts within each government assessed each
project. Members felt that the process
for approval was cumbersome as both the Lead Member and Lead Officer had
already presented the projects in 2017.
Members were advised that the Programme was based on a Five Case Business
Model. Members
asked for details around the Yr Egin project as this
had been completed without UK/WG’s approval and were advised that the programme
lead ie Trinity Saint David’s University, had taken
on the financial risk should the project not be approved. Members
expressed concern that, after a long process the Joint Agreement was signed,
the 11 projects agreed in principle (with flexibility if required) and that
both the UK and WG now had unprecedented input in approving the projects. It had been two years since the Joint
Agreement had been signed and not a lot had happened since. It was a 15 year programme and Members
questioned whether the approval process was too complicated and as such holding
up the Programme as a whole? Did the
Joint Agreement need reviewing? This may
possibly be addressed via one of the reviews being carried out. In
response the Economic Development Manager advised that the informal process,
where the projects were considered by both governments prior to consideration
by the Programme Board, etc., was resulting in numerous comments and versions
of the 3three business cases submitted.
Members expressed concern that this was holding back progress in
delivering the Programme overall. It
was noted that some of the projects could be delivered without City Deal monies
– and Members asked whether the current projects could be changed. It was noted that projects could be changed
however it was not possible to add any schemes at this stage as there was no
additional funding available. The
Manager advised that there was a ‘flow chart’ for this and offered to attend a
future meeting to explain the process.
Members noted that City Deal Funding was a catalyst for attracting
private funding. At
the end of the informal process between the governments and the Regional
Office, it was noted that the Regional Office would determine when the process
was complete and the project would then be forwarded to the Programme
Board. It was noted that there were
regular meeting between both governments and the Regional Office, every three
to four weeks. The
three projects currently with the UK/WG governments for approval had been with
them since the start of December 2018. Members asked when the Programme Office anticipated the final projects would be ... view the full minutes text for item 3. |
|
Presentation on the Skills and Talent Regional Project PDF 1 MB Minutes: Committee
received a presentation from Jane Lewis from Carmarthenshire County Council in
relation to the Skills and Talent Regional Project. The project was working in partnership to identify
the skills and training needs for the region over the next 15 -20 years. The project was contained in the first
tranche as it impacted on the other projects making up the programme. New skills were vital to the delivery of the
other projects within the Programme. The
project aimed at building Gross Value Added (GVA) and ground work had already
begun. It
was noted that, at present, the project sat under the Regional Learning and
Skills Partnership for South West and Mid Wales and would transfer once the
project had been approved. Members
agreed that it was very important to improve skills, but asked how these would
be retained in the region? This would be
difficult as pay rates varied throughout the country, with this region, in
particular, being lower paid than most other areas. It was hoped that the area’s lower cost of
living together with the area itself would encourage people to stay. Members
were advised that the project was with UK/WG governments at the informal stage. The
committee asked whether there would be an initiative in place to prepare school
leavers for work?
Would the project include vocational avenues in addition to academic routes. It was noted
that the project proposed to alter the engagement stage to fall within schools
to help pupils make the right decision for them and not at HE and FE level,
which it was believed was too late. It
was noted that the project was not able to access the Apprentice Levy. Members
asked whether the project would best be delivered within five years of approval
of the project and not five years from signing of the Joint Agreement thus
ensuring a wise spend – not rushed. When
asked, Ms Lewis agreed that this would be the better option although background
work had been carried out the main costs for the project was the writing of
relevant courses and getting these approved.
This would form the match funding referred to in the Business Case and
which had already been agreed by the HE and FE bodies. Members
were pleased that agreement had been reached with the HE and FE bodies however
it was noted that austerity measures also extended to them. Members also asked whether there were
sufficient number of teaching staff available locally to carry out the project
and were advised that teachers would also require upskilling in some areas. In
relation to the levels of skills, it was noted that the Government wanted an
increase in Levels four - seven whilst the project would also focus on levels
one - three which were likely to be school leavers and to then increase their
levels through the different stages. Members were keen to know whether similar projects were being looked at to ascertain best practice and were pleased to note that this ... view the full minutes text for item 4. |
|
Presentation on the Homes as Power Stations Regional Project PDF 1 MB Minutes: The
Joint Scrutiny Committee received a presentation from Gareth Nutt the Director
of Environment in Neath Port Talbot Council on the above project. Members
were advised that the Full Business Case (minus the procurement stage) was submitted
to both the UK and Welsh Governments in August 2018. It was noted that all three regional projects
were linked not only to each other but to the rest of the Programme as a
whole. The Registered Social Landlord (RSL)
sector already supported the pilot project, thus the holdup at UK/WG level was
questioned. It
was noted that once approval had been given it would be necessary to establish
a Programme Team and a local supply chain, however no advance funding was
available to put these in place before approval by UK and WG and the release of
funding. It was estimated that 70% of
the supply chain would be local. Members
asked whether there was sufficient capacity in the construction sector to
deliver this project?
The link with the skills project was noted in addressing some of the
issues. Each
of the four local authority areas had a project which could come under the Homes
as Power Stations (HAPS) umbrella and approval of the project was therefore
required as soon as possible to enable monitoring and evaluation of these
schemes going forward. The
presentation outlined the numbers and costings associated with new build and
retro fitting of existing properties and asked for details of how the figures
were arrived at. In response Mr Nutt
advised that the figures were mainly estimates based on regional delivery
costs. The various Local Development
Plans (LDP) allocations for new builds also fed into the proposals. It
was confirmed that each individual authority’s scheme could continue without
City Deal Funding, however a co-ordinated approach would be the better option
in order that best practice could be adopted throughout the City Deal
area. The
project was at the informal stage with both UK and Welsh Governments and it was
noted that a response had been given to their last query in November 2018. Members
asked how long it would take to evaluate and implement the project and were
advised that it would be five years after approval had been given, subject to
staff being in place. In
relation to the work to new builds, the additional costs would be passed on to
the buyers – would this inhibit the project?
The Principality Building Society was exploring the possibility of
developing a mortgage product aimed at properties which had negligible fuel
costs as a result of this project. It
was noted that there was an assumption that the four local authorities would
use their collective leverage to deliver the project, however Welsh Government
should be lobbied to put in place measures, for example building regulations,
to secure greater private sector engagement. It was agreed that the same issues applied to this project in relation to the time scale for implementation in that the project could be delivered five years ... view the full minutes text for item 5. |
|
Presentation on the Digital Infrastructure Regional Project PDF 896 KB Minutes: Members
received a presentation from Mike Galvin a consultant working on the Digital
Infrastructure Regional Project. The committee
was advised that the original Heads of Terms which were enclosed with the
agenda had been drawn up in March 2017 and had been amended significantly due
to changes in government policy. The
Business Case was being written taking into account mapping, coverage and
economic need, etc. The four local
authorities met on a regular basis and had a good working relationship with the
university, mobile providers and health authorities. Of the £55m allocated to the project, £25m
was public money with the remaining £30m being private investment. It
was confirmed that the project would require five years from the date of
approval in order to establish the infrastructure. There was frustration in the time taken as no
money was being released to progress any of the research and development work
required to prepare the Business Case. Hopefully
the first draft of the Business Case would be submitted shortly for
consideration at the iterative stage with both the UK and Welsh
Governments. Members
were advised that recruitment for a Manager had started in November but had
been put on hold when the reviews had commenced. Carmarthen had taken the risk on board and
was paying for the Consultant and any associated revenue. Members
asked whether this was a risk or opportunity for the private sector and noted
that only three providers were interested in taking part in the project. It would be necessary to encourage providers
to take part in the project. Members
asked what had changed from the initial vision of an internet coast and the
transatlantic cable and were advised that the transatlantic cable would now,
due to security of connectivity, land in London and have an interchange
to service other areas of the UK. It
was noted that there was a resource problem in preparing and submitting the
Business Case. |
|
Project Updates (Verbal) Minutes: Members
noted that there was no update in relation to this item. |
|
Updated Risk Register (Verbal) Minutes: Members
noted that there was no update to this item. |
|
Financial Monitoring (Verbal) Minutes: Members
noted that there was no update to this item. |
|
Minutes: Members
discussed the work of the Joint Scrutiny Committee going forward and requested
that the following issues be programmed into the Work Programme:- ·
That meeting be convened on a bi monthly basis, on alternative months to
the Joint Committee; ·
That the 151 Officer be asked to attend to discuss the financial issues
surrounding the City Deal, including the financial risk attached to each of the
projects and the City Deal Programme as a whole; ·
That information be sought on the anticipated outcomes of the City Deal
Programme and a stabilised GVA; ·
That consideration be given to inviting both UK and Welsh Government to
attend a future meeting to discuss the mechanism for approval of City Deal
Projects and why there is a hold up in approving the projects and releasing the
funds. |