Minutes:
The
Joint Scrutiny Committee received a presentation from Gareth Nutt the Director
of Environment in Neath Port Talbot Council on the above project.
Members
were advised that the Full Business Case (minus the procurement stage) was submitted
to both the UK and Welsh Governments in August 2018. It was noted that all three regional projects
were linked not only to each other but to the rest of the Programme as a
whole. The Registered Social Landlord (RSL)
sector already supported the pilot project, thus the holdup at UK/WG level was
questioned.
It
was noted that once approval had been given it would be necessary to establish
a Programme Team and a local supply chain, however no advance funding was
available to put these in place before approval by UK and WG and the release of
funding. It was estimated that 70% of
the supply chain would be local. Members
asked whether there was sufficient capacity in the construction sector to
deliver this project?
The link with the skills project was noted in addressing some of the
issues.
Each
of the four local authority areas had a project which could come under the Homes
as Power Stations (HAPS) umbrella and approval of the project was therefore
required as soon as possible to enable monitoring and evaluation of these
schemes going forward.
The
presentation outlined the numbers and costings associated with new build and
retro fitting of existing properties and asked for details of how the figures
were arrived at. In response Mr Nutt
advised that the figures were mainly estimates based on regional delivery
costs. The various Local Development
Plans (LDP) allocations for new builds also fed into the proposals.
It
was confirmed that each individual authority’s scheme could continue without
City Deal Funding, however a co-ordinated approach would be the better option
in order that best practice could be adopted throughout the City Deal
area.
The
project was at the informal stage with both UK and Welsh Governments and it was
noted that a response had been given to their last query in November 2018.
Members
asked how long it would take to evaluate and implement the project and were
advised that it would be five years after approval had been given, subject to
staff being in place.
In
relation to the work to new builds, the additional costs would be passed on to
the buyers – would this inhibit the project?
The Principality Building Society was exploring the possibility of
developing a mortgage product aimed at properties which had negligible fuel
costs as a result of this project.
It
was noted that there was an assumption that the four local authorities would
use their collective leverage to deliver the project, however Welsh Government
should be lobbied to put in place measures, for example building regulations,
to secure greater private sector engagement.
It
was agreed that the same issues applied to this project in relation to the time
scale for implementation in that the project could be delivered five years
after approval and the establishment of the Programme Team. In addition it was agreed that a site visit
to the pilot scheme in Neath be arranged when the
Joint Scrutiny Committee was held in the Neath Civic Centre.
Supporting documents: