Minutes:
Members
received a presentation by the Economic Development Manager
It
was noted that the 11 agreed projects were at different stages, with three
projects having gone through the process and were awaiting United Kingdom and
Welsh Governments’ (UK/WG) approval. The
criteria for approval was in line with the green book of H.M.Treasury
and Members were advised that experts within each government assessed each
project. Members felt that the process
for approval was cumbersome as both the Lead Member and Lead Officer had
already presented the projects in 2017.
Members were advised that the Programme was based on a Five Case Business
Model.
Members
asked for details around the Yr Egin project as this
had been completed without UK/WG’s approval and were advised that the programme
lead ie Trinity Saint David’s University, had taken
on the financial risk should the project not be approved.
Members
expressed concern that, after a long process the Joint Agreement was signed,
the 11 projects agreed in principle (with flexibility if required) and that
both the UK and WG now had unprecedented input in approving the projects. It had been two years since the Joint
Agreement had been signed and not a lot had happened since. It was a 15 year programme and Members
questioned whether the approval process was too complicated and as such holding
up the Programme as a whole? Did the
Joint Agreement need reviewing? This may
possibly be addressed via one of the reviews being carried out.
In
response the Economic Development Manager advised that the informal process,
where the projects were considered by both governments prior to consideration
by the Programme Board, etc., was resulting in numerous comments and versions
of the 3three business cases submitted.
Members expressed concern that this was holding back progress in
delivering the Programme overall.
It
was noted that some of the projects could be delivered without City Deal monies
– and Members asked whether the current projects could be changed. It was noted that projects could be changed
however it was not possible to add any schemes at this stage as there was no
additional funding available. The
Manager advised that there was a ‘flow chart’ for this and offered to attend a
future meeting to explain the process.
Members noted that City Deal Funding was a catalyst for attracting
private funding.
At
the end of the informal process between the governments and the Regional
Office, it was noted that the Regional Office would determine when the process
was complete and the project would then be forwarded to the Programme
Board. It was noted that there were
regular meeting between both governments and the Regional Office, every three
to four weeks.
The
three projects currently with the UK/WG governments for approval had been with
them since the start of December 2018.
Members
asked when the Programme Office anticipated the final projects would be approved
and whether the five year deadline agreed by the Joint Committee for completion
of all projects could be met and if not could there be an extension?
The
Joint Scrutiny Committee was advised that the five year deadline had been
agreed in order to allow enough time for the outputs of the projects to be
realised and measured. It was confirmed
that the 11 projects leads had confirmed that the five year deadline could be
met.
The
second tranche, which consisted of four projects was well developed and would
hopefully be submitted soon.
In
relation to the various reviews being undertaken, Members asked when these
would be reported to the Joint Committee and were advised that this would be at
the meeting to be held on the 28 March, 2019.
It
was agreed that the concerns of both the Joint Scrutiny Committee and Officers
in relation to the time taken to give approval to projects be conveyed to the
Joint Committee together with the UK and Welsh Governments as it was felt that
it was proving a risk to the delivery of the Programme within the
timescales. In addition Member asked
that the Joint Scrutiny Committee’s views be taken into consideration at the
same time the reviews were being considered.
Supporting documents: