Minutes:
Officers presented Members with the South West
Wales Corporate Joint Committee (SWWCJC) draft budget for the 2025/26 financial
year, which included the proposed levy charge to the constituent authorities.
The Committee was informed that the constituent authorities must be
notified of the levy for the upcoming financial year by 31 January 2025. It was
mentioned that discussions had already started to take place with each of the
Local Authorities and Elected Members regarding the requirements of the SWWCJC
budget setting process.
The circulated report set out three different options (Option 1, Option
2 and Option 2B) in terms of budget setting for the SWWCJC. It was highlighted
that the options were quite consistent with previous years; setting a
continuity budget or increasing the workflow, through the budget, to try and
achieve the objectives of the SWWCJC. Officers added that there was still work
to be undertaken in terms of understanding the level of activity of some of the
functions and workstreams.
Officers clarified the detail of the three different options as follows:
· Option 1 – Continuity
budget.
· Option 2 – Requested
budget.
· Option 2B – Requested
budget with the use of reserves.
It was stated that Officers were recommending Option 2B, which was set
out in Appendix C of the circulated report. Noting that the discharge of
reserves was proposed to be carried out over a planned period of three years;
this was to help prevent the need to request significantly increased levies in
the future, recognising the challenges that the constituent authorities face
individually in terms of their budget setting process.
Additional detail regarding Option 2B was provided to the Committee,
highlighting that this option accommodated the requests that had been received
from three out of the four workstreams; Appendix C detailed the expectations
that could be delivered through the budget for Transport, Energy and Economic
Development.
Further to the above, it was explained that there were currently some
challenges around defining the work and expectations of the Planning
workstream; therefore, the funding could not be provided in the same context.
However, it was noted that the leads for this workstream had previously
confirmed that this was an acceptable position, and they were working with
Welsh Government to identify further funding and clarity on delivering the
programme of work.
A discussion took place in regard to the overall budget position of the
SWWCJC, if Option 2B was to be approved. It was noted that the draft budget for
2025/26 was demonstrating an estimated expenditure of £710.3k. Officers
explained that they had looked at options to try and standardise the levy
charge on the constituent authorities, to keep it the same as what was charged
in the 2024/25 financial year; if this was to be considered, Officers will be
required to utilise the reserves to fund that. As previously, mentioned
Officers would be seeking to do this over a three-year period as follows:
· £153.5k in 2025/26
financial year.
· £167.7k in 2026/27
financial year.
· £182.2k in 2027/28
financial year.
It was anticipated that the reserves would be in the region of £964k at
the end of the 2024/25 financial year; therefore, if the reserves were to be
utilised over a three-year period, it would leave a balance of £460.8k in the
reserve pot by the end of that period.
In addition to the above, it was proposed that a small levy be charged
to the two National Park Authorities in the 2025/26 financial year; as the
Planning workstream develops, there would be a responsibility on those National
Park Authorities to contribute to the Planning function. Officers stated that
the proposed charge for the 2025/26 financial year was under £1k in total;
however, this would increase over time as the cost of delivering this
workstream increases. It was noted that bringing in this principle for the
upcoming financial year was critical in the overall position, especially as it
was something that the SWWCJC had delayed doing the last two years when setting
the levy charge.
In concluding the projection and recommended proposal, Officers stated
that Option 2B would enable work to be delivered for the workstreams, whilst
keeping the levy charge the same for the constituent authorities for the next
three years (with the addition of the levy charge to the National Park
Authorities); monies from reserves would be utilised over a steady period which
would allow the SWWCJC flexibility to develop as required.
The Committee was informed that the proposals contained within the
circulated report were presented to the SWWCJC Overview and Scrutiny Sub
Committee; Officers provided an overview of the feedback that was received from
the membership of that Committee. It was highlighted that concerns were raised,
from some Members, in regard to the levy charge; they discussed reducing the
levy due to the pressures on each of the constituent authorities in terms of
setting their own budgets. It was explained that their views were noted,
however there weren’t any formal recommendations proposed from the Overview and
Scrutiny Committee.
In terms of the response to the concerns raised, the Chief Finance
Officer (Section 151 Officer) for the SWWCJC highlighted the reasons for
proposing to keep the levy the same; particularly as the SWWCJC was continuing
to develop and increase its capacity. Officers views was that it would be
sensible and reasonable to set the levy the same as previous years, and to
carry a certain amount of contingency and flexibility in the budget; especially
as there were still unknown factors moving forward with developing the SWWCJC
and delivering its objectives.
Leaders welcomed the feedback from the Overview and Scrutiny Committee,
especially acknowledgement of the pressures that Local Authorities were facing
in terms of budget setting processes. However, the overall consensus was to
agree Option 2B in order to ensure that the SWWCJC had the funds to allow the
workstreams to develop accordingly and to ensure there was a suitable level of
reserves for future demands.
It was recognised that Brecon Beacons National Park Authority formed
part of three different Corporate Joint Committees; it would be important to be
mindful of this when setting the levy in the future.
RESOLVED:
· That the budget for the South West
Wales Corporate Joint Committee, for the 2025/26 financial year, be set and
approved at £710.3k (as detailed in Appendix C of the circulated report
(Requested Budget with the use of reserves)).
· That the Levy Charge, based on population to the
constituent authorities, be approved as follows:
Local Authority Levy 2025/26:
City and
County of Swansea Council (Levy) - £191,188
Carmarthenshire County Council (Levy) - £151,281
Neath Port Talbot CBC (Levy) - £114,094
Pembrokeshire County Council (Levy) - £99,414
Brecon Beacons NPA (Levy) - £147
Pembrokeshire Coast NPA (Levy) - £672
Total = £556,797
Supporting documents: