Minutes:
The
Committee were provided with an update on the current position of the
development of the Strategic Development Plan (SDP).
Members
were informed that Officers across the region had engaged with Welsh Government
as part of an informal consultation; this was conducted around two years ago
and was regarding an informal SDP manual. It was noted that the SDP manual was
going to be produced by Welsh Government and would provide a consistent
approach in terms of SDP preparation across Wales.
It
was stated that whilst the informal consultation took place some time ago,
Officers were still awaiting publication of a formal consultation regarding a
draft version of the guidance; there had been numerous delays from Welsh
Government in terms of issuing that document for consultation. It was expected
that the draft manual will not come forward until Spring 2025, with final
publication by late Summer / early Autumn 2025. The Committee were informed
that this document was vital in terms of enabling and facilitating SDPs across
Wales as it will set out the approach that needed to be taken.
Officers
added that the preparation of the SDP was a mirror image of what individual
Councils were doing with their Local Development Plans (LDPs), and there was a
lot of work involved in preparing these plans.
It
was confirmed that numerous discussions had taken place regarding financial,
and staff related resources to deliver the work programme; the financial
commitment to deliver an SDP was going to be substantial, with estimated
figures of between £2.5 and £3.5 million. It was noted that Officers and
Politicians had been lobbying Welsh Government in terms of providing sufficient
and adequate resources in order for Corporate Joint Committees (CJCs) to move
forward with this work programme.
A
discussion took place in regard to the importance of having adequate staff
available to prepare the SDP and deliver the work programme; individual Local
Authorities were currently involved in preparing their Replacement Local
Development Plans (RLDPs). Therefore, at this point in time, it was not an
option to divert Local Authority staff away from that particular work programme
in order to progress work relating to the SDP. The Committee were informed that
Officers across Local Authorities had received clear instruction from Welsh
Government that they were not to stop progress with their RLDPs.
In
terms of the current position, it was stated that the South West Wales
Corporate Joint Committee (SWWCJC) will not be in a position to commence any
work on the SDP until the resource issue was resolved.
Officers
mentioned that they had received correspondence from the Cabinet Secretary
regarding the requirements to produce a delivery agreement by the end of 2024;
however, for the reasons mentioned above, this was not going to be achievable
at this time. It was explained that a delivery agreement for the SDP will be
similar to any Local Development Plan; it will set out the timetable, the scope
of any community involvement scheme and the resources required. Officers were
not in a position to clarify this detail at this time.
Reference
was made to the North Wales and Mid Wales regions, who were in a similar
position to the South West region. It was Officers understanding that Cardiff
City region had developed an early draft of their delivery agreement; however,
there was currently no detail in that document of how they were going to
resource that process.
Whilst
there hadn’t been any substantive work done to date on the SDP, it was
highlighted that Officers from Local Authorities across the region were
continuing to work collaboratively in terms of evidence-based studies; each
Local Authority was bringing forward their RLDP programmes and had been working
together in terms of potential joint studies. It was mentioned that these
pieces of work will provide the building blocks for the SDP, as and when it
could be progressed.
Reference
was made to the legal implications detailed in the circulated report,
specifically regarding the potential of a judicial review. Officers explained
that it was now set out in statute and regulations that regions were required
to bring forward an SDP at some point; it was important for the report to
identify that there was an element of inherent risk with not being in a
position to progress with the SDP work programme.
Members
queried how not progressing with the SDP will impact on the wider work of the
CJC. It was confirmed that this wouldn’t prevent work progressing in other work
streams; however, it will be important to ensure that all the relevant
documentation and work programmes aligned. It was stated that the SDP will
ultimately present a land use planning framework for the region, however it
should be aligned with the Regional Transport Plan and
any documentation regarding economic development and energy.
A
further discussion took place in regard to the SDP manual. It was mentioned
that the working draft that Officers had sight of, from the initial
consultation, was very substantive and comprehensive in nature. Officers
expressed their views on the way in which this documentation could have been
developed.
The
Committee was informed that all Local Authorities were in receipt of
consultation documents from Welsh Government, which contained a number of
proposals. Officers highlighted that one of the proposals related to the
timescales associated with RLDPs. It was explained that there was a requirement
to review RLDPs every four years, however Welsh Government could be looking to
extend that review cycle to six years; this could help Local Authorities and
CJCs in terms of having capacity within the region to progress SDPs. Officers
stated that this showed that Welsh Government acknowledged that capacity and
resources were an issue.
It was noted that Officers previously had a briefing from Welsh
Government and one of the topics of discussion was the role of the CJC and how
they could feed into the strategic planning consultation; Welsh Government were
expecting to understand what CJCs think of their role in terms of linking into
the planning system as a whole, not just through the SDP.
Reference
was made towards the timescales of developing and implementing the SDP. It was
noted that the initial SDP manual suggested SDPs could be brought forward
within five years; albeit there was recognition that it would likely take
longer than this. It was reiterated that the draft delivery agreement that
Cardiff City region had produced indicated a six-year timeline. Officers stated
that this process involved a lot of work before getting to a position where the
region had an adopted SDP in place.
Supporting documents: