Decision:
The
report was noted.
Minutes:
Jonathan Burnes gave
members an overview of the January to March and highlighted some of the key
portfolio level summaries and the project and programme updates.
On the dashboard, members
were advised that there is no overall change to the status, but there have been
a few movements within staffing and resources for digital infrastructure. For Yr Egin delivery has moved from green to amber status.
On the risk register
members were advised that there are currently 25 portfolio level risks, five are red risks.
There is no change from quarter three. Members were advised that the five red
risks are around construction costs, TAN 15 which is the flood risk management
maps, in year spend, slippage and delivery of benefits. Officers that they all
have mitigations associated with them.
Members were advised
that there were 4 amber risks which were closed since the quarter three reporting and these relate to the time frame of the end of
current EU funding programmes which is completed. The unallocated £5.3 million
of CDL funding which is now allocated through Neath Port Talbot Council for the
skill centre operations of the PMO. That moved from the risks to the issues
because Ian Williams has departed and the Co-opted members not attending
programme and joint programme boards and joint committee, and they are
attending, and officers continue to monitor those.
Officers advised that
there are no red issues and the only red issue which was previously on there
was Campus funding agreement that now has been signed and resolved, and that
can come off the issues register.
In terms of the
quarterly reports, there was an increase in jobs created from 567 from quarter
three to 597 and investment has increased from £272 million to £289 million.
In terms of the
construction impact assessment, members were advised that business cases have
been written and they are now going into procurement to look at what the
funding gap is from what officers thought it would cost to what it actually does cost.
Members were advised
that the headline gap is £43 million but through the mitigations that are
detailed in the report, it has now reduced to £12 million, and officers are
still working on the mitigations on that residual impact.
Members were advised
that the key mitigations are to secure additional funding, revisit the
construction brief and opening dialogue with the contractors.
Officers explained that
the projects identified as experiencing slippage are the waterfront, Yr Egin, digital infrastructure, campuses and support
innovation low carbon growth. All of those are subject to the change management
process and reporting them through the government arrangements accordingly.
Members asked about the
benefits summary and noted that compared to the last report Pentre Awel was
created 23 jobs, but the innovation matrix was not included before, and this is
the first time it was in this benefits summary.
Officers explained that
the Innovation Matrix is nearing its completion, and they have construction
jobs created. Officers had thought they had reported some before, but the six
that has been identified in this quarter are likely to increase again in future
quarters. Officers explained that they can only report once the contractor and
the subcontractors have reported their numbers of jobs created, particularly
through construction and once it's into operation. Then it is about the
organisations that reside within it and how they grow. Officers advised that
these may have to be evaluated separately.
Members were informed
that the innovation matrix is completed, and it is being fitted out internally
for tenants to reside within it led by University of Wales, Prince St David.
Officers were asked if
these jobs will be included in the benefit summary of the report or are they
going to move somewhere else?
Officers confirmed that
in terms of jobs created, they will just be accumulated in the report and more
jobs will come through the pipeline for each of the projects as they as they
get reported.
Members were advised
that the 597 jobs include the ones from innovation matrix campuses and Pentre
Awel from that quarter, quarter four.
Members noted that a
line had been introduced in the report that hasn't been in previous reports in
relation to the benefit summary on page 135. Which shows six additional jobs in
the innovation matrix. Officers advised that it shouldn't be in the report
because the innovation matrix is part of Swansea Waterfront business case, and
it should be part of that project instead.
Officers believed that
the officer that dealt with it was just highlighting that that was the
addition. It is not part of Swansea Council's lead element. It is part of
Trinity Saint David’s lead element. It should be the nine headline projects and
programmes and officers will correct that.
Members asked what the
mitigations officers are looking at for the 12 million pounds shortfall
Officers explained that
the £12 million is an indicative figure and it hasn't moved on. Officers
advised that in the last report they had still identified a £12.75 million gap
and in terms of the key mitigations there are three. The first is securing additional
funding which could be through the lead deliverer or through governments or
through private sector. The second mitigation option is revisiting the
construction brief and the third is delaying some projects and opening dialogue
with contractors.
Officers advised that
they are experiencing a lot more dialogue with the primary contractors and also with the supply chains because the subcontractors
also have a lot more dialogue with the primary contractors because they don't
make a lot basically and they want to make sure that they deliver in quality.
Members noted that in
the benefits report there were no jobs targeted but jobs had been created in
skills and talent and digital infrastructure and asked why this was.
Members asked if there
was a way that they can have an updated figure, even if it's emailed to them
about the jobs total, because 6.15% is quite low and noted that they were 3
months behind in reporting.
Officers explained that
when the business cases were written, particularly for digital infrastructure
and skills and talent, they were fully regional projects and cover all of South West Wales. Members were advised that these were
enablers, and they didn't directly create jobs. Officers advised that the jobs
are created through the other projects and programmes but because of a lot of
work being done particularly for digital infrastructure and skills and talent,
jobs are being created directly and indirectly through the projects and
programmes.
Members were told that
this is why jobs created will show up in the report but there is no requirement
in those business cases to evidence that and they will be captured throughout
the process.
Officers advised that in
terms of the targets and the timing of reports, as soon as they go through
joint committee, they are publicly available through Democratic services
officers and Jon Burnes will make sure that they are the relevant projects as
members will likely just want key, key summaries.
Members were also
advised that for the reporting of some jobs must go through an evaluation to
qualify what officers are saying. And this will make things harder to get exact
figures and explained that even though it's at 6% officers know that number is higher,
but it just hasn’t gone through the evaluations to qualify them.
Officers explained that
if you are going to verify the claims made by people before you, particularly
the indirect ones then the direct ones are claimable because there is an
auditable trail.
For more indirect jobs
created as a consequence of building, they have to go
through an evaluation with the evidence to make sure that it's verified
externally (Ideally), but it could be verified internally as well.
Members noted that they
see this as 6% of jobs achieved. But the pubic may read it as 94% not achieved
and asked if this could be seen as a negative for the project.
Members also asked does
this reflect similarly to the issues with the Gross Value Added (GVA) in that
it's quite hard to quantify?
Members used Yr Egin as an example of a building that has been up and
running for a while and it's got 117 out of the 400 jobs. Members asked if Yr Egin phase 2 was really going to achieve the other 300
jobs when that's done?
Members asked if this a
case of the numbers from the initial business are hard to achieve or if any of
them realistically achievable because of all of the
changes that have happened.
Officers advised that
this is currently year eight and there was a false start with City Deal at the
beginning and getting all of the business cases
through the approval process, but it is now on track for delivery, officers
believe they are realistically achievable.
In relation to
evaluations, Officers have advised that they have done an evaluation, and it is
the first evaluation of a city deal and it hasn’t been reported through any
governance board.
Later this financial
year members will see and be able to scrutinise the first evaluation, which is Yr Egin looking at the economic impact of Yr Egin phase one that will include jobs and various other
things as well. they couldn't have evaluated during the kind of COVID lockdown,
and they needed a clean operational year and therefore evaluated 22/23 as the
operational year.
Members were also given
as an example, Swansea arena which will need to have a year or two of operation
before they can evaluate it. Officers explained that they are going to evaluate
the arena to look at the wider economic impact, including jobs, jobs as part of
that.
Officers hope that the
evaluation framework will hopefully put to rest some of the concerns around the
numbers because it will come through as buildings come into operation and the
wider impact of those.
Members noted that the
projects are making a massive impact in terms of regeneration and positivity
for the region, across the region.
Members stated that they
look forward to the evaluation on Swansea Arena because there are 25 full time
jobs and note that there are lots of part time jobs other jobs that are around
it in the Green Cafe.
Members felt that it
will be critical for them to understand how that process is carried out because
that is the whole basis of what the city deal is about and stated that it is
incredibly important that that process is transparent and is also publicly available
as well.
Officers advised that at
a portfolio level, that they had held sone ‘Meet the City Deal’ events within
the last quarter and noted that in Neath Port Talbot was the Margam Orangery
event which had over 100 people in attendance. Part of the annual report will
talk about the four Meet the City Deal events in Pembrokeshire,
Carmarthenshire, Swansea and Neath Port Talbot.
Officers felt that they
were extremely beneficial and successful.
Members were advised
that the slipway and the pontoons in Pembroke Dock Marine are now starting to
be used and a lot of the other projects within the Pembroke Dock Zone are now
securing and leveraging funds through other mechanisms and officers were happy
to see that pipeline of activity behind the infrastructure happening.
In terms of campuses,
the funding agreement has now been signed and a re-profile is under way and
since the report was published, there has been progression on the procurement
process for Singleton phase one.
Members were advised
that in terms of support and innovation, low carbon growth, the key areas are
Bay Technology Centre is now just over 50% of occupancy and there's a pipeline
of inquiries around the office space and lab space that they have available.
Officers advised that
with the air quality monitoring project, there's a company called Ricardo who
has done a review report, and they are presenting that to board and looking at
what the next steps are.
Members were informed
that Pentre Awel is progressing and there is over 2000 training weeks in the
construction phase to date. They have 31 apprenticeships undertaken within the
build and 44 new entrants. Pentre Awel are currently working on updating their
business case, this will help them reprofile the economic, commercial and
financial cases of their business case for zone one and future zones (2,3 &
4).
In relation to digital
infrastructure, they have been awarded their first 5G investment fund which is
linked with the campuses project, and this is considered by officers as an
example of good cross fertilisation across the portfolio and it is on track for
completion.
Officers advised that
the dark fibre phase one procurement exercise is complete, and the preferred
supplier has been appointed.
Members were informed
that for the waterfront that the hotel developments were going to cabinet last
week for decision to appoint a preferred collaborator around what is the Arena
hotel.
Officers advised that
there is lots of work happening with the 171 Kingsway around respective
tenants.
Members were advised
that the innovation matrix is progressing well and according to plan and
they're doing the fit out now for the tenants to move in as soon as possible
within the next month or so.
In relation to Yr Egin, members were advised that it is going on to phase
two and are looking at what change notification change request is required for
that and the solution. Officers are yet to receive anything formally from
Trinity Saint David on that.
Members were also
informed that for skills, they are now up to 19 pilot projects, which officers
considered to be great especially because of the spread of it across all the
different sectors with all the different training providers and private sector
companies is phenomenal from an officer’s perspective.
The report was noted.
Supporting documents: