Minutes:
Members were provided
with information on the current position regarding costed decarbonisation
delivery plans for Net Zero, and the wider funding challenges associated with
this.
The circulated report
informed the Committee of the approach taken by Swansea Council, following
direction from the Welsh Audit Office (WAO), in order to meet Welsh Governments
Net Zero ambition. It was noted that Councils needed to fully cost their action
plans and ensure that they were aligned with Medium-Term Financial Plans.
Officers from Swansea
Council explained that they developed a high-level costed delivery plan, which
was a way of monetising what the ask was going to look like. A discussion took
place regarding the findings of that piece of work, which included buildings
and energy, street lighting, fleet and grey fleet. It was explained that this
process provided an indication of how much money would be needed to take this
work forward; this was noted to be a high cost for Local Authorities.
It was expressed that
Local Authorities were committed to taking this work forward in order to
achieve Net Zero, however there would need to be some changes from a Welsh
Government level, in order to assist them in doing so.
Officers from
Carmarthenshire Council provided their experiences and confirmed that they had
adopted a similar approach and had similar figures to Swansea Council.
It was stated that it
would be beneficial if there was a consistent approach throughout Wales in
regard to this work stream, which would allow all Local Authorities to come up
with a consistent methodology. This statement was support by Members, who
expressed that the biggest benefit of doing this was around the commonalities
where Councils could co-procure, as well as the ability to find priorities as a
Region. It was added that it would be even more beneficial if this was carried
out on a National basis.
External advisors, from
Welsh Government Energy Service, highlighted that there was a climate strategy
panel task and finish group set up with a focus on procurement; particularly
looking at the ways in which the Energy Service could support Local Authorities
going forward.
Reference was made to
offsetting, and the fact that even though Councils purchase 100% renewable
energy, this wasn’t counted in terms of offsetting. Members expressed their
frustration with this and felt that it was a missed opportunity.
Following on from the
above, it was noted that Welsh Governments view was that offsetting should be
the last resort, and that the focus should be on all reasonable efforts to
reduce emissions. The Committee was informed that there was a team within the
Welsh Government Energy Service, who were working hard on determining what
offsetting might look like. In addition, there was work being undertaken to
identify how the guidance could be updated; with a focus on renewables and
purchasing.
Officers from Neath Port
Talbot Council and Pembrokeshire Council also provided an overview of the work
they were progressing. Representatives from Neath Port Talbot confirmed that in
January 2024, they commissioned the Carbon Trust to assist in formulating a Net
Zero costed plan; they were expecting this to be concluded by October or
November 2024. Representatives from Pembrokeshire Council noted that they had
taken a different approach to the other three Local Authorities and were
progressing on a case-by-case basis in order to try and keep it cost neutral.
Members were provided
with the perspective of Brecon Beacons National Park and the areas they were
looking to address going forward. These were noted to be procurement and waste,
as these were the areas in which they had the largest remaining footprint.
A discussion took place
in regard to the short-term actions, including the asks of Welsh Government and
the associated barriers; and what tangible steps the Energy Sub Committee can
take to support the effort.
One of the barriers
highlighted from Officers was the process of obtaining grant funding; in
particular the timings associated with getting the schemes ready for submission
and the timings in which Local Authorities must spend the grant. It was noted
that if the process was to stay the same, Councils would need more resource to
be able to do this better.
It was explained that
there was a piece of work that Officers were undertaking, in conjunction with
the Welsh Government Energy Service, in terms of consolidating and advancing
the asks from Welsh Government. It was added that a workshop would be arranged
to discuss this in more detail; the outcomes of the workshop will be provided
in a future meeting of the Energy Sub Committee.
The Committee were
provided with a brief overview of the Net Zero Scenario Planner that was under
development by the Welsh Government Energy Service. It was explained that this
tool would gather data from each of the 22 Local Authorities across Wales,
principally around building energy usage, street lighting and fleet. It was
stated that the information will be mapped up to the year 2030, with the
purpose of applying change in emissions factors from turning on certain
interventions, so that Councils can identify what happens to their emissions if
they implement the measures. Members were informed that for fleet and street
lighting, this would be a move to electric vehicles and a switch to LED
lighting; and for buildings there were a few options that essentially build
from a decarbonisation only option, to add in energy efficiency measures and
renewables to make this more affordable.
In terms of timelines
associated with the planner, it was noted that the data request had been
submitted and would be re-received by the end of June 2024. It was added that
Officers would spend the summer of 2024 building the models, before running
training events in September/October of 2024 to demonstrate to Local
Authorities how to use the tool; following his, a summary report will be sent
to the Welsh Local Government Association (WLGA) of the overall findings, and
then it would be over to each Local Authority to test the tool and run
scenarios.
Following on from the
overview, a discussion took place in regard to the use of a single framework
for 22 Local Authorities, all with different positions; and how ever-changing
technologies will also impact the use of the tool. It was acknowledged that
there were going to be limitations to the tool, and the Energy Service were
going to have to make some assumptions to enable to model to work at this
scale; there wasn’t sufficient resource to be able to produce a custom model
for each Local Authority. External advisors stated that they had customised it
to try and make it as relevant as possible; however, there will be differences
for each Local Authority.
Members were provided
with assurances that the Energy Service would be able to assist Local
Authorities with their detailed and technical feasibility review; this would
feed into the scenario planner.
It was expressed that
the Committee would benefit from understanding what the procurement plan for
fleet would look like, and if there was visibility across the Region.
Following the
discussion, the report was noted.