Decision:
The
report was noted.
Minutes:
The
Steve Edwards, Commercial Director, Milford Haven Port Authority. Gave a
presentation to members in relation to the Pembroke Dock Marine Update report. He
thanked members who had attended the site visit to Pembroke Dock in January.
The
presentation covered the following areas.
1) Progress update on the Pembroke
Dock Marine project;
2) Outcome of the Pembroke Dock
Marine Gateway Review, including recommendations and mitigating actions;
3) Pembroke Dock Marine business case
addendum.
4) Change notifications received from
the Pembroke Dock Marine project.
The
chair and members thanked officers for the site visit to Pembroke Dock and
stated that it had been informative and was worthwhile to see what's been
developed.
Members
noted that the critical stage of the project was the commercialization element
and asked how the progress was in terms of trying to get commercial partners
involved and specifically with the units if there are any other vacancies?
Members
were informed that when officers knew that the assets were coming to
completion, they started a networking campaign which included going to Ireland,
Europe, and England as well as speaking with all the different developers at
conferences showcasing when the assets will be ready.
Officers
looked at identification of markets in terms of understanding when fixed
offshore wind was commencing in Ireland and used the example for the ‘Dublin
Array’. Officers noted who was winning those competitions for Dublin Array and
marketing those assets directly to those types of organisations.
Officers
stated that the outcomes to date have been mixed but it is not going badly for
the first year. Officers explained that there is a company who are a boat
builder/repair company using the mega slipway. That company now has 67 metres
of slipway and with their crane, they are capable of even more room. This is
greater than the 20 meters of slipway they had previously.
Officers
advised that they have had interest from some wave and tidal developers however
the test and demonstration for the 400 megawatts floating offshore wind is
paused and none of the developers have gone into the low carbon electricity
generation Contracts of Difference (CFD) round. Officers had hoped that it was
going to be an immediate opportunity.
Members
were informed that some pontoons have been added on the back of the ferry
linkspan and the first bookings have come in, with items being birthed up
against them this week.
A
hydrogen developer is at the draught heads of terms status with officers.
Members
were advised that it is a shame that the Floating Offshore Wind Manufacturing
Investment Scheme bid was rejected because if had been accepted, an immediate
start to work on the other side of the port would have commenced and created an
integration facility which probably would then be needed by the, the test and
demonstration developers for their anchors change moorings. That element might
be a bit further away as a result. Officers are looking to seek alternative
financing for that, but their ambition is the same and they are going to work a
little bit harder.
Members
were informed that the biggest annex attached to the hangar is still available,
and currently options for that are being looked at. The two smaller units on
that building has one leased and another is almost leased pending contract
signatures.
‘Booster’
has taken the hangar annex on the eastern side of the port meaning there are 3
out of 4 either leased or are going to be leased with one vacant as a minimum.
The
report was noted.
Supporting documents: