RESOLVED: |
that the following
Appeal determined be noted as detailed in the circulated report. Appeal
Ref: A2014/0006 Installation
of a Wind Farm comprising five wind turbines up to 126.5 metres to maximum blade
tip height, with associated transformers, electrical substation and control
building, 82 metre anemometry mast, underground cabling, access tracks, site
entrance, river crossing and crane hard standings; and temporary construction
compounds, storage area and two temporary 82 metre high anemometry masts, at Mynedd Marchywel, between Rhos and Cilfrew, North of
Neath. Decision: Dismissed. |