Minutes:
Officers presented the
Internal Audit Update Report which contained details of the work undertaken
since the last Governance & Audit Committee meeting; this was a quarterly
report which informed Members of the current position and what had been completed
since the last meeting, including details of the audits that had been
undertaken and their assurance ratings.
One of the main points
highlighted was in relation to staffing issues; since the last Committee,
the Team had been impacted again by a very high level of sickness, with two
staff on long term sickness. However, it was mentioned that the sickness was
being managed in line with the Council’s policies and procedures.
Another
staffing matter raised was the long standing issue with regards to Assistant Auditor
posts. It was noted that these posts were traditionally very difficult to
recruit to, even when someone was recruited, they invariably left after a year
or so to work in accounts or elsewhere within the Council; this was part of a
wider issue across recruitment in Audit Teams in various Councils. Due to this
issue, Officers explained that they undertook a review of the staffing
structure; it was agreed to delete the Assistant Auditor post and replace it
with an Auditor Post. It was confirmed that this had been completed, and the
vacancy was currently being advertised on the Councils vacancy bulletin, with
the closing date of 6th of October 2022.
Members were informed
one member of staff had recently completed parts one and two of their
professional qualification, and another member of staff had completed part one
and was due to sit part 2 of the examination in early October.
The Committee passed on
their thanks to the two members of staff for
undertaking their professional qualification examinations.
A discussion took place
in relation to the impact on resource due to staff illness, particularly in
terms of the delivery of the Internal Audit Plan. Officers explained that focus
was on completing the high risk areas, and the high risk areas that weren’t
undertaken were brought forward into the current year; conversations then took
place with the Senior Management Teams to determine if the areas that weren’t
covered, still needed to be covered, or if the Team needed to be directing
their resource to other areas.
Officers stated that
Appendix One of the circulated report provided details of the published
reports, and the assurance ratings applied at the end of the audit.
It was noted that the assurance rating was received by way of a calculation;
taking into account the number of recommendations made within the report, the
likelihood that a failure to action the recommendations within six months could
lead to a significant system failure, and the impact of a significant system
failure. It was confirmed that this information was then entered into a
spreadsheet, a formula would be applied, and one of the following categories
would be applied to the report:
·
Category One, Substantial Assurance -
testing found good controls to be operating and generally required only minor
recommendations.
·
Category Two, Reasonable Assurance -
testing found some control which needed enhancing, and which would be achieved
by implementing the agreed recommendations.
·
Category Three, Limited Assurance -
testing revealed a number of areas where the enhancement was required, and in
those cases the Head of Service for that area would be required to provide a
written response advising of what actions had been taken to address the issues
raised.
·
Category Four, no assurance can be
given - testing revealed areas of significant concern, and the Head of Service
and/or Accountable Manager will attend the next meeting of the Committee to
provide Members with an update on actions taken, and also to answer any
questions that Members may have.
The following
questions were raised in line with Appendix One of the circulated report:
·
R40 - Crynallt Primary School –
The circulated report stated that it was found that a DBS disclosure was not in
place for two current governors at the school; Members asked why the DBS were
not in place. It was explained that the governors were new, and the DBS process
had been started, however not yet completed at the time of the audit.
·
R1 - Bryncoch Church in Wales
Primary School – The circulated report stated that a minor enhancement was
required in relation to Unofficial Funds; Members raised that there had been
issues in the past with monitoring the Unofficial Funds, and asked for further
information on this. Officers confirmed that they would find out the details of
the issue and provide an explanation via email to the Committee as to what the
issue was.
·
R2 - Coedffranc Primary School –
The circulated report stated that good controls were found to be in place in
relation to all areas tested, other than Purchasing/Procurement Card; Members
asked for the reasoning behind this. Officers
confirmed that they would find out the details of the issue and provide an
explanation via email to the Committee as to what the issue was.
Officers
made reference to Appendix Three of the circulated report, which consisted of a
response letter from the Chief Digital Officer, and another from the Head of
Planning and Public Protection; both of whom were responsible for the areas
which received limited assurance. It was noted that the letters provided
Members with information relating to what they had done since receiving their
audit report. It was clarified that for all audits that were undertaken, a
follow up post audit review was completed anywhere between one month and six
months after the audit, in order to check for compliance with the agreed
recommendations.
RESOLVED: |
That the report be noted. |
Supporting documents: