Minutes:
Officers
presented the Head of Internal Audit’s Annual Opinion on the internal controls,
governance and risk management arrangements operating within the Council during
the financial year 2021/22.
The main headline
of the report was noted to be the work undertaken by internal audit and
external regulators; following this work, Officers were in a position to
provide reasonable assurance that there were no significant weaknesses in the
overall control environment operating across the Council. However, it was noted
that the current risk management policy was not fully adhered to during the
previous financial year. Members were assured that risks were managed in the
usual way, and that the issues were around the reporting and updating of the
risks; there was currently work ongoing to revise the policy, which will be
taken to the appropriate Committees in due course.
Officers
stressed that in giving the annual opinion, at no time can they provide
absolute assurance; every system that operated within the authority could not
be tested every year, therefore Officers could only provide reasonable
assurance to the Committee based on the work undertaken.
Reference was
made to Appendix One contained within the circulated report, which provided
details of the achievement against the internal audit plan; as stated in the
body of the report, a considerable number of days were lost last year due to
sickness within the team. It was noted that a revised plan was brought to a
previous meeting of the Committee, which removed some of the lower risk areas,
which allowed Officers to concentrate on the higher risk areas.
It was mentioned
that Appendix 2 of the circulated report provided details of the Internal Audit
Team’s ongoing quality assurance and improvement plan.
Members asked for
further information in regards to the risk management policy not being fully
adhered to. Officers explained that the policy was due to be reviewed on a 3
year basis, with the review date set for 2021; that review was
delayed slightly, however there was now good progress being made on the review.
It was noted that there were delays in the reporting of the risks and updated
position to the appropriate Committee; Officers weren’t able to adhere to the
reporting frequency due to a number of reasons including a change in
administration and a delay in meetings taking place. Members were informed that
the Council had strengthened the personnel dealing with the risk management
policy, which should equate to a significant improvement going forward.
Reference was made
to the CRM (Customer Relationship Management) system solution that had
previously been discussed in the Governance and Audit Committee training
session. It was asked if progress had been made in implementing the digital
solution. Officers highlighted that work had been undertaken to move the
strategic risk register onto a Microsoft Excel based solution; it was ready to
be implemented, following discussions in the Corporate Directors Group and a
future meeting of the Governance and Audit Committee.
Following on
from the above, it was queried if some elements of the CRM system would be
digital, as well as those which were on Microsoft Excel. It was explained that
the operational risks, which were held on accountable manager level, were
included on the CRM system; the strategic risks were being maintained on an
Excel spreadsheet for the time being.
The circulated
report detailed that a total of 42 formal audit reports were issued, and only
one audit resulted in a limited assurance rating. It was asked if this meant
that 41 reports were positive. Officers confirmed that the 41 reports would
have either had a substantial assurance or a reasonable assurance rating.
A question was
asked in relation to quality assurance, and details relating to the last time a
quality assurance assessment was carried out on the team. It was confirmed that
2018 was the last time a quality assurance was carried out on the team; they
were due to be externally assessed again early in the new calendar year. The
Committee was informed that it would be carried out by way of peer review, with
the other participating Authorities in Wales; Neath Port Talbot Council would
be required to carry out a review on Caerphilly County Borough Council, and
colleagues in Conwy Council will be carrying out the review on Neath Port
Talbot Council.
In addition to
the above, Officers clarified that the Council followed the public sector
internal audit standards, and their external assessment template, when an
external review was being carried out. It was noted that each Council was
responsible for filling out a self-assessment to determine if the Council
complied, partially complied or did not comply; this assessment would then be
reviewed by the Council carrying out the external review, and they will ask for
documentary evidence to support the assertions that were made in the
self-assessment.
Members were
informed that previously, the Council undertaking the review held conversations
with a range of people in order to feed into the review; including the
Chairperson and Vice Chairperson of the Committee, the Section 151 Officer and
External Auditors. It was confirmed that a formal report will be written and
brought to the Governance and Audit Committee, once the review was complete.
RESOLVED: |
That the report be noted. |
Supporting documents: