Minutes:
Officers
informed Members of the updated Regeneration Action Plan following an
examination undertaken by Audit Wales.
Members were
pleased that Officers had taken on board a lot of the suggestions that were made
by Audit Wales. It was noted that the comments relating to communications were
reassuring; if the Council continued to make progress with the recommendations
detailed in the action plan, future projects could be benefited and it could
provide the public with confidence in what the Council was trying to achieve.
The importance of Community Benefits was also raised; it was reassuring that
the Council had acknowledge a better way of dealing with this matter, and that
Officers will be involved at an early stage for each project going forward. It
was mentioned that this was beneficial in order for the public to be aware of
the direct benefit from a project.
Officers
acknowledged that there were always improvements that could be made to various
elements of services; some of the barriers to this could be related to systems,
resources or a combination of the both. It was stated that the milestone
planner that was completed with the Media Team had been reinvigorated, in order
for them to have a much better idea of what projects were coming up; Officers
were hopeful that this will solve some of the issues that arise.
Following the
discussion, it was agreed that the Head of Property and Regeneration would
provide a report to the Committee on the subject of Community Benefits.
Members asked if
there were any further updates on the Welsh Government formula for flood areas.
It was confirmed that the position statement was the same as previously
reported to the Committee, and that there were still a lot of issues relating
to flood zones across the County Borough; the flood maps were known to change,
land could be taken off the flood zone list or added onto the list, and the
reasoning behind this could often be difficult for people to understand.
However, it was mentioned that the information on flood areas was improving
year on year, and was becoming more robust which will help the Council to make
the best possible decisions in regards to the utilisation of land. Officers
highlighted that the County Borough had some challenging areas with flood
mitigation, and in terms of taking developments forward was an expensive
process and was a risk, as the desired results may not be achieved at the end
of the process.
It was asked if
there was a process in which the Authority could challenge the decisions that
Natural Resource Wales (NRW) make in regards to flood land. Officers confirmed
that NRW could only be challenged on a case by case basis, as it would need to
be proven that the development in question was not going to put anybody else
into determent; this was a difficult and long process, which would involve a
lot of consultancy work by external specialists. It was stated that flooding
issues were becoming more prevalent, and NRW were doing their best with the
resources at hand, in order to understand where the impacts will be. Members
were informed that when the Council provides its data on flow rates etc., NRW
will look at the data and may need to change their model slightly; therefore,
their model will always be a constantly changing status, which was concerning
for developers as it would add to the risk element.
Officers were
asked if there was an update on the progress of obtaining monies from the
Levelling Up Fund. It was confirmed that there had been no further news on the
Levelling Up Fund or the Community Renewal Fund; if the Council were to be
successful in obtaining monies from this fund, they had a spend profile in
place for the rest of the year. Officers mentioned that a lot of organisations
who had been part of the bidding process, have had to change their spending
profile completely due to timescales and not having confirmation of monies. It
was hoped that the Council would have heard if it was successful or not during
the summer period, however Officers still had no indication of when they would
be receiving the decision; this caused an issue for the Council as it would be
difficult to get the spend out by the end of the financial year, which was
March 2022. Officers confirmed that they needed to start making decisions
imminently, as work needed to be completed on the projects; however, due to not
having indication on whether the Council had been successful or not, the
challenge will be having to conduct the work at a risk and potentially not be
able to re-claim some of the costings.
A discussion
took place in relation to the Shared Prosperity Fund; in regards to this,
Members highlighted that it would be beneficial to collaborate with Local
Members for the town centre areas. It was stated that the Shared Prosperity Fund
would follow on from the Levelling Up Fund; it was hoped that the timescales
given for this would be better than the previous, in order for Officers to
submit bids effectively. Members were informed that Officers had already
started working on project ideas to discuss with Members in the near future;
this will be beneficial as Members will have seen some of the projects that
Officers were hoping to submit, prior to the event.
It was queried
whether there was an indication as to what the priorities were going to be for
the Shared Prosperity Fund. Officers mentioned that the UK Government had
stated they had been inundated with bids for the Levelling Up Fund, which was
why the decision was delayed; this was an indication that there wasn’t going to
be a sufficient amount of money available due to the number of bids that had
been submitted.
The
Committee noted the report.
Supporting documents: