Minutes:
The
Chief Executive, Karen Jones, provided information with regards to the delay of
the issuing of the consultation report, subsequent to the tape recording which
appeared on social media. The decision to delay the consultation report was
taken to ensure some additional due diligence on the processes that the Council
has undertaken in bringing forward the advice. The decision-making processes
concerning the school reorganisation programme were considered as part of this
additional work. Following this work a report was produced. The conclusion from
the report indicates that the Council can take all assurances regarding its
systems and processes. Some recommendations have been made within the report
and this includes that meetings are accurately recorded so that openness and
transparency are maintained.
The
report has been shared with the Auditor General who has concluded that he does
not wish to undertake specific audit work at this present time. He has
acknowledged that there are some procedural items which need to be addressed
and he has asked for sight of the action plan in response to the
recommendations. He has also advised that when the Public Services Ombudsman
work is complete he will look at the findings at that time.
The
Public Services Ombudsman has advised that he is not aware of any issue that
will stop the report on the agenda being discussed at the meeting. He has also
advised that the focus of the remainder of his investigations will focus on the
member directly and not on the systemic or broader issues.
The
Director of Education, Andrew Thomas, was invited to provide an overview on the
item for discussion. Mr Thomas provided a brief update with regards to two
recent correspondence received, asking for reconsideration of the recommendation
within the report. Mr Thomas advised that the letters did not ask to be
circulated to Members. However Members will be provided with a copy of the
response to be sent to both organisations, irrespective of the outcome from the
meeting.
Members
were advised that the report indicates the decision is subject to a three day
call in, however it is intended for immediate implementation. The Statutory
Notice reflects the date. The reason for this is that if Members were in
agreement to progress the item, then the full statutory 28 days’ notice is all
within term time.
Mr
Thomas categorically stated that there was no intention to close any other
schools, other than the three mentioned and attached to the report to be
discussed.
Mr
Thomas went through some of the issues identified in the consultation. Members
were provided with a rationale for the chosen site of the proposed school. Mr
Thomas went through the size requirements of the new school with the pupil size
indicated and highlighted that the proposed area already had outdoor playing
fields etc. so these would not need to be sourced. Further, there are no other
sites within the area required to accommodate a school of the proposed size.
There
are health and well-being benefits identified within the report. The new build
also involves the building of a new 6 lane swimming pool and leaner pool. There
is no requirement to consult on this part of the development.
Traffic
was identified as a major issue within the traffic consultation responses. Mr
Thomas referred to previous schools developed including Cwm Brombil and Ysgol
Bae Baglan, where traffic management measures were also implemented. Due to the
amount of capital expenditure available in relation to the new build of a
school, there is an opportunity to consider traffic management within the area.
If the development goes ahead there will be a Traffic Impact Assessment
conducted. This will be undertaken by the appointed contractor and will need to
meet the required planning processes. The overall traffic management at the
proposed site should improve due to the rigorous nature of the processes and
requirements as part of a Traffic Impact Assessment.
Transport
and travel of pupils was discussed. The vast majority of pupils who would
attend the new school would live within 2 miles of the proposed site. Any pupil
who doesn’t live within a suitable walking route or within the 2 miles will be
entitled to assistance with transport. Requirements will be assessed closer to
the implementation date of 2024 based on the pupils who will be attending the
school.
Concerns
were raised about pupil standards and well-being. Mr Thomas referred to other
schools that have been created and prior concerns being raised by parents about
these items. However, Members were advised that when reviews of the schools
have been undertaken a year after they were opened none of the concerns raised
had manifested.
In
terms of the Welsh language impact, 25% of the staff would be fluent/fairly
fluent in Welsh. This would be a strength in that the skills would be focused
in one place so that the development of Welsh as a second language would be
strengthened and go over and above the current arrangements in schools.
Members
discussed the proposals outlined. Several areas of concern were raised.
Members
expressed concern about 3 year olds accessing nursery provision on foot in
Llangwig and also children who access school transport. The report advises that
nursery education is not statutory therefore there is no entitlement to assistance
with school transport. Concerns have also been raised with regards to accessing
breakfast club and after school activities. It was noted in the report that
transport will not be provide for these activities.
Mr
Thomas acknowledged that some parents may experience difficulty with accessing
nursery provision. With regards to breakfast club, it is the school
responsibility to ensure that all pupils have access to breakfast and after
school activities. The local authority are legally obliged to provide a
breakfast club if the school ask, but the timings of such provision are
determined by the school.
Members
expressed their concern about the community aspect of the school closure.
Members were curious with regards to what the officers consider to be a
community and how the report presented can advise that the school closures will
have no adverse effect on the community. Concern was expressed with regards to
local shops and the importance of the passing trade of people walking to the
local school.
Mr
Thomas asked Members to consider if the positive benefits of the reorganisation
proposals outweigh the negative impacts. He referred to the significant school
community that will be created at the new school, and the well-being
improvements linked to the additional support for children with additional
needs. Also, the across stage phase work with Cwmtawe School. Mr Thomas was
satisfied that well-being objective 2 is satisfied by the proposal.
Concerns
were raised about traffic at the new site and the road that leads into the
area. Members accepted that the contractor would need to deal with the traffic
at the new site itself, but Members were concerned about the actual road access
into the town. It was put forward by a Member that residents believed that a
new road would need to be built to accommodate any new school. Mr Thomas
confirmed that any new traffic management provisions as part of the planning
requirements for the new school would be funded as part of the 21st
Century Schools programme.
Members
queried how the budget was being set in relation to the works which had not yet
been identified. Mr Thomas advised that there was a substantial budget set from
the £22.5million funding available for the school. However, should any
necessary works exceed budget, there is an opportunity to go back and seek
further funding from Welsh Government.
Members
referred to the Well Being of Future Generations Act and the negative effects
that the development of the new school may have on three of the identified
well-being goals.
Mr
Thomas confirmed the start of the process began in 2017 when a Strategic
Outline Programme was placed before Members. It outlined the development of a
new 3-16 school. In response to consultation this was then changed to the
current proposal.
Mr
Thomas went through the consultation that has been undertaken and the
consultation period was extended to make sure that people could respond
accordingly. Mr Thomas advised that the report has addressed the themes raised
by the consultation. There have been no substantial reasons to change the
recommendations within the report.
Members
raised concerns about the Welsh Travel Act and the effect that the new school
will have. Member queried if there would be future penalties imposed upon the
Council in relation to this. Officers confirmed that Welsh Government have
approved the business case for the school, so there would be no penalties.
Members
raised concerns about the effect of the new school on Welsh medium schools
within the area. Mr Thomas advised that from experience, this had not been the
case with other schools that had been opened, and numbers in Welsh medium
schools continue to rise. Members queried what ongoing monitoring would be
carried out and what action would be taken should there be a negative impact on
the Welsh medium schools.
Mr
Thomas confirmed that all aspects of the new curriculum would be the
responsibility of the leadership and Governing Body at the new school to ensure
that it is delivered accordingly. Members raised the issue of nursery pupils
attending school in Powys as opposed to attending the proposed new school and
this would essentially reduce the budget of the new school.
Members
recognised that pupils from Godre'rgraig School were currently in temporary
accommodation. Pupils are expected to stay there until the proposed new school
opens in 2024. There are currently reports in progress to understand the
remedial works required at the site. If the new school development proposals
fail, then the Council will consider other options for those pupils. There has
been one site considered within Godre'rgraig for the primary school, which
could be an extremely costly site to develop. If this site was developed, the
whole process for the current plans stop and a whole new business case would
need to be developed for Welsh Government.
MR
Thomas advised that if a new school in Godre'rgraig is developed alongside the
proposed school of Alltwen and Llangiwg then this would require a school budget
half a million pounds a year. Members were advised that when NPTCBC borrow to
build new schools this is done over 30 years as it is a capital investment,
therefore, this would be £20 million pounds over 30 years. This budget would be
subsidised by every other primary school in Neath Port Talbot. Mr Thomas
confirmed the proposal to develop two schools had been given consideration,
however officers did not think it is an effective use of public funds. Whilst
Members were concerned about the treatment of Godre'rgraig Primary School,
officers stressed the value for money concept and that the whole school
community would carry the revenue costs.
Members
queried if there were any timescales attached to the funding from Welsh Government.
Mr Thomas confirmed there were no timescales or financial penalties if the
scheme was to be delayed.
Member
queried if the application for the Deed of Dedication had been submitted for
the proposed site? Further, where the alternative parcel of land is sited? Mr
Thomas was unsure if the application had yet been submitted however he
confirmed that there was no reason to believe why the application would be
refused.
Mr
Thomas explained how primary schools are maintained. There is a sum of £1.2million
annually available to maintain all primary schools within the Borough. That
money is allocated on a Building Surveyor’s assessment of worst case first. Mr
Thomas confirmed at least a third of the funding goes on statutory testing.
Member were informed this budget keeps schools open in terms of maintenance
however doesn’t bring the school up to 21st century standards.
Members
queried how the capacity figures for the number of children attending the
proposed new school were acquired and if they have been independently verified.
Mr Thomas advised that there is a responsibility to develop a school which is
future proofed. Members were reminded that Welsh Government are funding 65% of
the proposed development and agreed with the projected pupil figures which have
been put forward. The figures take account of the number of housing
developments planned and the number of children living in the catchment who
could claim a place at proposed school.
Members
briefly touched upon Pontardawe swimming pool and queried why a 6 lane pool was
being replaced with another 6 lane pool. Mr Thomas advised that the current
pool was past its economic life and is at significant risk of business
continuity economic failure, resulting in eventual closure.
Member
queried why the consultation report refers to an ‘improved’ location for the
swimming pool. Mr Thomas referred to the 2000 pupils who would have access to
the facility, thus improving the economic, commercial opportunities and also
the wellbeing of those students accessing the facility. It will provide access
to assist with the development of lifelong habits which will help to promote a
healthy lifestyle.
Some
Members provided their input with regards to experiencing the same situations
within their wards. Often members of the public’s fears were allayed once the
new school were in situ. The community use of the new buildings has vastly
improved in areas where new schools have been developed.
Mr
Thomas confirmed that 21 people responded in favour of the proposed
development. Members were advised that it is common that more people will take
part in consultation who are against a proposal, as opposed to those who
support the proposals.
Members
queried how the new proposal fitted in with encouraging active travel. Mr
Thomas referred to previous records which indicated that 49% of children
travelled to Godre'rgraig School by car. Mr Thomas referred to the overall
wellbeing of the children and how the proposals contributed positively to this
through the facilities and the extracurricular activities that will be provided
as a result of the development.
Members
raised concerns that the business plan for the proposed development was
submitted to Welsh Government before any consultation was undertaken with the
community.
A
recorded vote was proposed and seconded and agreed in line with required
procedures.
The vote was undertaken to
determine which Members were for and against the recommendations detailed in
the circulated report. The results of the vote were as follows:
Following scrutiny, the majority of the committee was supportive of the proposals to be considered by Cabinet.