Agenda item
Application No. P2014/0825 - Foel Trawsnant
Installation of 11 wind
turbines with a maximum tip height of 145m to generate up to 33 MW, together
with ancillary development including substation and control building, on site underground
electrical cables, stone site access tracks, temporary construction compounds,
turbine foundations and temporary crane pads. (Amended application which seeks
a reduction in the number of turbines from 13 to 11, an increase in maximum tip
height of turbines from 120m to 145m) at Foel Trawsnant, Bryn, Port Talbot.
Minutes:
Officers
made a presentation to the Planning Committee on this Application (Installation
of 11 wind turbines with a maximum tip height of 145m to generate up to 33 MW,
together with ancillary development including substation and control building,
on site underground electrical cables, stone site access tracks, temporary
construction compounds, turbine foundations and temporary crane pads. (Amended
application which seeks a reduction in the number of turbines from 13 to 11, an
increase in maximum tip height of turbines from 120m to 145m) at Foel Trawsnant, Bryn, Port Talbot)
as detailed in the circulated report.
RESOLVED: |
That
in accordance with Officers’ recommendations, Application No. P2014/0825 be
approved, subject to the conditions detailed in the circulated report. |