Variation
of condition 1 of Planning Permission P2007/1413 (Granted on Appeal on the
07.05.09) to allow for the extension of time for the commencement of
development and variation of conditions 3 (reference to all works in
Environmental Statement and to allow a maximum tip height of 100m and maximum
blade diameter of 82m), 9 (borrow pits), 14 (highway improvement works to
facilitate revised access route) and 15 (internal access tracks) - MYNYDD Y
GWRHYD, North of Pontardawe, East of Cwmgors
Minutes:
Variation of Condition 1 of Planning Permission P2007/1413
(Granted on Appeal on the 07.05.09) to allow for the extension of time for the
commencement of development and variation of conditions 3 (reference to all
works in Environmental Statement and to allow a maximum tip height of 100m and
maximum blade diameter of 82m), 9 (borrow pits), 14 (highway improvement works
to facilitate revised access route) and 15 (internal access tracks) at MYNYDD Y
GWRHYD, North of Pontardawe, East of Cwmgors.
RESOLVED: |
that the application be approved in accordance with the
Officer’s recommendation, as detailed in the circulated report, and subject
to the following amendment to the wording of Condition No.16 in respect of
the required Traffic Management Scheme (TMS) to clarify the need for the TMS
to incorporate details of all delivery routes (including abnormal loads and
stone deliveries), as stated in the circulated amendment sheet:- (16)
Notwithstanding the submitted information, no development shall take place
until a Traffic Management Scheme (TMS) has been submitted to and approved in
writing by the Local Planning Authority. The TMS shall set out all
proposed delivery routes, timings of works and include details of any
alterations/amendments to the existing A474 on route through Pontardawe and up to the site location. This shall
include temporary speed reduction measures (if applicable), give way
markings, times of operation, removal of existing street furniture,
roundabouts, kerb alignments etc. that allows safe delivery of the wind
turbines. The development shall be carried out in accordance with the
approved Traffic Management Scheme including the reinstatement / restoration
of temporary works necessary to allow for the deliveries associated with this
development. Reason: In the
interest of highways safety |