Minutes:
Decision:
That
Authority be delegated to the Director of Environment and the Head of
Engineering and Transport, to enter into a Deed with Network Rail, as set out
in the circulated report.
Reasons for Decision:
1. The Deed will satisfy Network Rail’s requirement for a design
warranty which is part of their standard Business Asset Protection protocols.
2. The provision of the Deed will allow the submission for the
Station change at Port Talbot Parkway to be submitted by Network Rail to the
Department of Transport for approval of the works.
3. To promote the aims and objectives of the Economic
Regeneration, Planning and Transport strategies and the Single Integrated Plan
– Prosperity for All.
Implementation of Decision:
The
decision is an urgent one for immediate implementation,the
Chair of the Scrutiny Committee had agreed to this course of action and therefore
there would be no call-in of this
decision.