Venue: Remotely via Teams
No. | Item |
---|---|
Welcome and Roll Call Minutes: The
Chair welcomed everyone to the meeting. |
|
Chairs Announcements Minutes: There
were no announcements. |
|
Declarations of Interest Minutes: There
were no declarations of interest received. |
|
Homes as Power Stations PDF 559 KB Minutes: The Chair welcomed Lisa Willis and Oonagh Gavigan to the
meeting. Members were provided with a presentation on Homes as Power
Stations, by the Project Manager, Oonagh Gavigan. The project was approved by Welsh and UK Government in July 2021.
It is a regional project led by Neath Port Talbot Council. The aim of the
project is to facilitate the HAPS Approach. This is the integration of energy
efficient design and renewable technologies in 10,300 new and existing homes. The project has a number of key objectives. These include
the adoption of the HAPS concept mainstream; to create smart/intelligent energy
efficient homes; to reduce carbon emissions; to reduce fuel poverty; to improve
heath & wellbeing; to create and support a skilled supply chair and the
sharing of information/data to enable this to happen. To achieve the objectives
there are several funding streams available, including the Financial Incentives
fund which is £5.75m and the Supply Chain Development Fund which is £7m. The project will work alongside the Skills & Talent
programme to ensure that people have the necessary skills and training to
provide confidence in the programme. The project will procure an independent organisation to
monitor and evaluate the different designs and technologies to ensure ongoing
learning and evaluation of the programme. The budget for this is £1m. This will
ensure a comprehensive and accurate set of data and results to inform the
project as it progresses. Areas included in the evaluation include performance,
environmental conditions, fuel costs and poverty, environmental behaviour,
costs and health and wellbeing improvements. The information obtained will be
shared through the open access knowledge hub. Ms Gavigan went through the project pilot scheme development
located in Neath. The scheme was one of the earliest projects, funded by Welsh
Government innovative housing programme. It include a number of partners and
created 16 homes to store and create solar energy. The completion of the project was delayed until November
2020. Sero have been appointed to continue to collect data from systems and
tenants. Ms Gavigan gave an update on the overall project to date.
The Project Manager has been appointed. Discussions have now begun with IT
experts to determine how the data will be best shared and how a sharing hub
will be created which will be accessible to interested parties. Currently a map
of initiatives is being decided to add value and improve the HAPS concept.
Officers are also currently mapping a supply chain to support applications to
the supply chain development fund. The next steps are to recruit the rest of the team and to
establish and gain legal approval to disseminate the funding streams. The team
will also commence the procurement of the monitoring and evaluation early next
year. Members queried where the funding in terms of private and public investment is currently at. From the public sector there is significant interest in the project. From the private sector, particularly small to medium enterprises, it is difficult to get them involved until they need to be, as ... view the full minutes text for item 4. |
|
Financial Monitoring Report PDF 1 MB Minutes: Richard Arnold went through the report. The report related to Quarter 1. Members were advised that
Quarter 2 should be ready for the next meeting (following approval at the Joint
Committee). Mr Arnold outlined the financial structure. The Joint
Committee includes the support functions and the portfolio investment fund is
the grant to be drawn down over 15 years. An independent financial statement is prepared for the City
Deal which is independent of the host authority, Carmarthenshire, and the
statement is also independently audited. Appendix A is based on the forecast outturn position for the
year. There is a five year agreed operational budget for the Deal in place,
which is currently operating in year 2. However, the City Deal is in year 4, as
the Joint Committee existed in shadow form to appoint and there was a six month
translation period into the formal accounting structure to deal with it. Mr Arnold went through the year end projection for the Joint
Committee, Joint Scrutiny Committee and also the Portfolio Management Office. Funding contributions are made up of grant revenue
contributions and the eight partner contributions. Officers advised that the reason that there is a deficit is
due to a timing issue. This was due to a delay in the business cases being
approved. The project is currently being supported from the reserves. However
there were no concerns about this and it is anticipated that the funding would
even out. The portfolio investment fund is an outturn position based
on 15 years and is based on the original head of terms. Against these the deal
is demonstrating a deficit on investment of about £37m (3%). The investment
package at year 15 is projected £1.237billon. The Programme Investment Forecast table outlines specific
project level information. There are estimated 4% revenue costs within the
budget. In terms of the Portfolio Investment Fund members queried if
this could be broken down annually. How much have private companies invested
and how much have the individual authorities put in through their borrowing
powers to date? Officers advised that this could be brought before a future
meeting. Members were keen to ensure that forecast projects of income and spending
were being met. The benefits realisation profiles will split down the
benefits at the portfolio level for the 15 years. They will provide GVA jobs
and investment anticipated up to the end of the portfolio. They will also
provide the wider programme and project benefits being delivered. Mr Burnes advised Members that GVA is a macroeconomic
indicator and they are seeking clarity from Welsh and UK Governments with
regards to how to attribute it to a project and build it up to a wider regional
setting. Further how it should be presented to Governments. Members discussed the funding gap created by the anticipated
project completion dates and the drawdown of funding from Government. Members
acknowledged this is where authorities will need to borrow to support the
funding gap. |
|
Internal Audit Recommendations - Update PDF 793 KB Minutes: Mr Jonathan Burnes provided a verbal update on the Internal
Audit recommendations. There were four key recommendations from the audit – one
is near completion, two are closed and one will be ongoing. The first recommendation was around formal agreements. They
involve the four organisations – two health boards and two universities. It was
confirmed they are not signed partners on the Joint Committee Working
Agreement, but they are partners within the City Deal. Agreements have been
sent to all four bodies, three have been received back and the fourth one is
expected imminently. With regards to the declarations of interest, a process is
now in place. There has been a 93% response rate and officers confirmed that
they are awaiting clarification with regards to the interest forms suitability
for the Economic Strategy Board. Secondly, in terms of the risk scoring methodology, this was
required to be reviewed as part of the Internal Audit recommendations. It
required consideration of the inherent and residual risk. This is now complete.
The third recommendation was in relation to capturing the
achievement of outcomes, outputs and impacts. The aim is to ensure that
detailed benefits realisation monitoring is in place for the next quarter (Q3).
At the end of the financial year, the outturn position should be clear and this
can then be monitored against the business case projection. From this point and
ongoing there should be a fully operational benefits realisation plan in place. The last recommendation related to private sector funding.
The recommendation required careful monitoring of this funding and ensuring
that contingency planning was in place should the funding not materialise. In
response to this there is quarterly monitoring, a framework has been created
for engagement of commercial business activity which needs to be approved by
the four local authorities. Members queried the access of the public to the declarations
of interest. In respect of this, at the time there are ongoing discussions with
regards to whose declarations are going on i.e. members and/or officers.
Declarations will be placed on the website when this has been determined.
Members suggested that officers should also be included. Concerning the risk management, Members queried if the new
flood maps been included on the risks as they pose a significant risk to some
projects. Officers confirmed that this has been cascaded down to project level
and taken into account. Projects are proceeding as planned. Members asked officers, in relation to the risk assessment,
if the ones that have changed can be brought to members’ attention as opposed
to just providing the full risk assessment. Officers confirmed that this model
was already in place and would be presented at the next meeting. |
|
Swansea Bay City Deal Meeting Protocol PDF 509 KB Additional documents: Minutes: Jonathan Burnes provided a brief outline of the document. Members drew officer’s attention to 5.1 agenda setting.
Members asked for clarification on the wording as it suggests that the PMO are largely
setting the scrutiny agenda. Member confirmed the scrutiny committee sets the
agenda, but will work with the PMO on the collation of the information required
for the agenda. Members agreed draft wording in relation to the agenda clause
and send it across to the PMO for consideration. Members also noted the quorum on 3.8 indicated 8 members,
however the quorum was in the process of being reduced to 6. This would be
amended when the new quorum was approved by all four authorities. The Committee agree to send draft wording to the PMO to for
suggested changes to the wording in terms of agenda setting. |
|
Gateway Review and Action Plan PDF 523 KB Additional documents:
Minutes: The Gateway Review is a strategic review carried out by
external officers. It’s a three day review which considers how the programme
can move forward. The review took place in July and had an amber/green rating
on delivery. There were eleven recommendations from the review. Four were
key recommendations and six were advisory recommendations. Mr Burnes briefly
went through the recommendations and updates as outlined in the reports
provided. All recommendations will be considered equally by the Programme
Board. Members advised that they will be interested to learn how
this committee will fit into local governance arrangements in view of the
Corporate Joint Committees that will be coming forward in the future. |
|
Forward Work Programme 2021/2022 PDF 531 KB Minutes: Members
expressed an interest in viewing the Joint Committee forward work programme. Members
noted this item. |
|
Urgent Items Any urgent items (whether
public or exempt) at the discretion of the Chairperson pursuant to Section 100B(4)(b) of the Local Government Act 1972 Minutes: There
were no urgent items. |