Appointment of Chairperson Minutes: Agreed that Councillor M.Harvey be appointed Chairperson for the meeting. |
|||||||||||||||||||||||||||||||||
Declarations of Interest Minutes: No declarations of interest
were received. |
|||||||||||||||||||||||||||||||||
Minutes of Previous Meeting PDF 82 KB Minutes: Decision: That the Minutes of 2 July 2021,
be approved. |
|||||||||||||||||||||||||||||||||
Re-allocation of Highway Capital Monies released by 2020/21 Grant Funding PDF 147 KB Additional documents: Decision: Having given due regard to
the first stage Integrated Impact Assessment that approval be granted for
additional works to be carried out as part of the 2021/2022 Works Programme, as
detailed in the circulated report. Minutes: Officers
highlighted that the items in the report were priority safety issues. Decision: Having given due regard to the
first stage Integrated Impact Assessment that approval be granted for
additional works to be carried out as part of the 2021/2022 Works Programme, as
detailed in the circulated report. Reason for Decision: To maintain assets for which
the Council is responsible and address community concerns in relation to same. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Renewal of lighting at Manor Drive, Glynneath PDF 84 KB Additional documents:
Decision: Having given due regard to the
first stage integrated impact assessment, that approval be granted for officers
to seek permission and formal agreement from Aberpergwm Estate to enter Manor
Drive and renew lighting under the Public Health Act, as detailed in the
circulated report. Minutes: Officers
highlighted a number of these had already been dealt with as part of the
investment programme of the Council, and were applying the same process that
had been carried out under the main renewal programme. Decision: Having given due regard to the
first stage integrated impact assessment, that approval be granted for officers
to seek permission and formal agreement from Aberpergwm
Estate to enter Manor Drive and renew lighting under the Public Health Act, as
detailed in the circulated report. Reason for Decision: To address the issue of life
expired street lighting infrastructure in Manor Drive, Glynneath.
Implementation of Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Neath Town Centre Lighting Column Replacement PDF 75 KB Additional documents: Decision: Having given due regard to
the first stage Integrated Impact Assessment, that approval be granted for the
street lighting column replacement work in Neath Town Centre to be funded by a £60K
one-off savings in the lighting energy budget associated with the ongoing SALIX
funding low energy lamp replacement work, as detailed in the circulated report. Minutes: It was noted that if the
lighting was not renewed separate columns and separate power supplies would
need to be put in place, hence the measures highlighted in the circulated report.
Decision: Having given due regard to the
first stage Integrated Impact Assessment, that approval be granted for the
street lighting column replacement work in Neath Town Centre to be funded by a
£60K one-off savings in the lighting energy budget associated with the ongoing
SALIX funding low energy lamp replacement work, as detailed in the circulated
report. Reason for Decision: To address ageing
infrastructure and community needs. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Electric Charging Infrastructure for Fleet Vehicles PDF 727 KB Additional documents:
Decision: Having given due regard to the Integrated
Impact Assessment: 1.
That the development of Electric Vehicle (EV) charging
points and Photovoltaic Solar Panels
at the Quays to support the Councils EV fleet transition plan, as detailed in
the circulated report, be approved. 2.
That approval be granted for an application for grant
funding be submitted to Welsh Government Energy Service (WGES) and Office for
Zero Emission Vehicles (OZEV) to partly finance the project and to further
authorise £516k of borrowing over 25 years to fund the project. 3.
That development of an EV charging policy for staff to
utilise this service, be approved. Minutes: Decisions: Having
given due regard to the Integrated Impact Assessment: 1. That the development of Electric Vehicle (EV) charging
points and Photovoltaic Solar Panels
at the Quays to support the Councils EV fleet transition plan, as detailed in the
circulated report, be approved. 2. That approval be granted for an application for grant
funding be submitted to Welsh Government Energy Service (WGES) and Office for
Zero Emission Vehicles (OZEV) to partly finance the project and to further
authorise £516k of borrowing over 25 years to fund the project. 3.
That development
of an EV charging policy for staff to utilise this service, be approved. Reason for Decisions: This proposal will support the
Councils decarbonisation agenda and forms part of the actions in the DARE
strategy. It will also support the planned transition of the Council Fleet to
zero emission vehicles in line with W.G’s ambitions, as set out in Welsh
Governments Prosperity for All Document of 2019, a Low Carbon Wales Proposal 4. Implementation of
Decisions: The decisions will be implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Zero Emissions Fleet Transition Plan PDF 272 KB Additional documents:
Decision: Having given due regard to the
Integrated Impact Assessment: 1. That the Fleet Transition Plan, as detailed in the
circulated report, be approved. 2. That the submission of the Fleet Transition Plan to
the Welsh Government Energy Service by the due date (22 October 2021) in
line with the requirements set out in Welsh Governments Prosperity for All
Document 2019, a Low Carbon Wales, be approved. Minutes: Decisions: Having given due regard to the
Integrated Impact Assessment: 1.
That the Fleet Transition Plan, as detailed in the
circulated report, be approved. 2.
That the submission of the Fleet Transition Plan to
the Welsh Government Energy Service by the due date (22 October
2021) in line with the requirements set out in Welsh Governments Prosperity for
All Document 2019, a Low Carbon Wales, be approved. Reason for Decisions: The Fleet Transition Plan will
provide a definitive timeline of when vehicles are to be renewed and what they
are to be replaced with. The Transition Plan is a Management tool which will help
the Council budget for the increased costs that will be incurred with E.V’s.
and identify any saving that may arise from the transition. Implementation of
Decisions: The decisions will be implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
List of Approved Contractors PDF 395 KB Decision: Having
given due regard to the Integrated Impact Assessment approval be granted for
the List of Approved Contractors be amended as follows: Companies to be added to
the List of Approved Contractors:
Minutes: Decisions: Having
given due regard to the Integrated Impact Assessment approval be granted for
the List of Approved Contractors be amended as follows: Companies to be added to
the List of Approved Contractors:
Reason for Decisions: To keep the List of Approved
Contractors up to date and as far as possible, ensure a competitive procurement
process. These recommendations to be
adopted for the purpose of supplying a List of Approved Contractors for
invitation to tender within the relevant category. Implementation of
Decisions: The decisions will be implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Welsh Government proposed 20mph default speed limit across Wales PDF 333 KB Minutes: It
was noted that officers would be seeking to submit the Councils consultation to
Welsh Government following the full Members Seminar which would be held on 27
September 2021. Members
questioned how feasible it was to limit traffic to 20mph and how popular was it
with the public, officers explained that they understood and shared Members
concerns and would be working closely with ward Members and our internal
communications team in working with individual communities as the 20mph default
progressed. It
was highlighted that with reference to feedback from the community in Cilfrew which was used as a pilot, the community were
largely supportive of the pilot, though noted that public there were happy in
the cul-de-sac location, but officers would be meeting with individual ward Members
with regard to the main arterial routes across the county borough moving
forward. Officers
explained that they would be working closely with Ward Members before
submitting a plan to Welsh Government. Decision: That
the report be noted. |
|||||||||||||||||||||||||||||||||
Footway/cycleway link to Eglwys Nunnydd and St Davids Park, Margam PDF 280 KB Additional documents:
Decision: That having given due regard to
the Integrated Impact Screening Assessment: 1. That approval be granted to construct a
shared footpath/cycleway to serve the residents of Eglwys
Nunnydd and St Davids Park,
Margam. 2. That the £550k within the Highways
Improvement programme be allocated to this scheme from within the Council’s
existing Capital programme, profiled over two consecutive financial years
2021/2022 and 2022/2023 to facilitate the phased delivery of the scheme, be
approved. 3. That the Director of Environment and
Regeneration be granted delegated powers to enter into agreements with land
owners to secure land to facilitate the construction of the footway/cycle path.
4. That
the proposed construction work be undertaken by the Council’s Streetcare Services over the two year period. Minutes: Officers explained with
regard to the query on page 211 and 212 of the circulated report in terms of
speed, it was
confirmed that it should state ‘a
reduction in the National speed limit along the A48 route from 60mph to 40mph’. The Local Member for the Margam Ward thanked officers for their hard work. Decisions: That having given due regard to
the Integrated Impact Screening Assessment: 1. That approval be granted to construct a
shared footpath/cycleway to serve the residents of Eglwys
Nunnydd and St Davids Park,
Margam. 2. That the £550k within the Highways
Improvement programme be allocated to this scheme from within the Council’s
existing Capital programme, profiled over two consecutive financial years
2021/2022 and 2022/2023 to facilitate the phased delivery of the scheme, be
approved. 3. That the Director of Environment and
Regeneration be granted delegated powers to enter into agreements with land
owners to secure land to facilitate the construction of the footway/cycle path.
4. That
the construction work be undertaken by the Council’s Streetcare
Services over the two year period. Reason for Decisions: To provide a safe walking and
cycle footpath for the residents of Eglwys Nunnydd and St Davids Park and
the wider community in the interest of road safety. Implementation of
Decisions: The decisions will be implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Glais to Pontrdawe PDF 207 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the 40
mph Speed Limit Traffic Regulation Order at the A4067 Glais
to Pontardawe (Neath Port Talbot Council boundary to Pontardawe), as detailed in the circulate report, and if no
objections are received that the proposals be implemented on site as
advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the 40
mph Speed Limit Traffic Regulation Order at the A4067 Glais
to Pontardawe (Neath Port Talbot Council boundary to Pontardawe), as detailed in the circulated report, and if
no objections are received that the proposals be implemented on site as
advertised. Reason for Decision: To help reduce traffic speed
in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Cilfrew PDF 211 KB Additional documents:
Decision: Having given due regard to
the integrated impact that the objections be overruled to the proposed 20 mph
Speed Limit Traffic Regulation Order at Cilfrew
Village, Neath (Various Streets, Cilfrew)
(Revocation) and (20 mph Speed Limits) Order 2021, as detailed in the
circulated report, be implemented on site as advertised and the objectors be
informed of the decision accordingly Minutes: It was noted that this is
part of the Cilfrew 20mph pilot. Decision: Having given due regard to
the integrated impact that the objections be overruled to the 20 mph Speed
Limit Traffic Regulation Order at Cilfrew Village,
Neath (Various Streets, Cilfrew) (Revocation) and (20
mph Speed Limits) Order 2021, as detailed in the circulated report and be
implemented on site as advertised and the objectors be informed of the decision
accordingly. Reason for Decision: To help reduce traffic speed
in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Cimla Road, Neath PDF 206 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
Individual Disabled Parking Place traffic regulation order at No. 135 Cimla Road, Neath, SA11 3UE, as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
Individual Disabled Parking Place traffic regulation order at No. 135 Cimla Road, Neath, SA11 3UE, as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Reason for Decision: To allow the successful
applicant to maintain their independence and quality of life. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Blaengwrach PDF 129 KB Additional documents:
Decision: Having given due regard to the integrated impact assessment that approval be granted to advertise the proposed Chain Road, Blaengwrach, Glynneath – Proposed No Waiting, Loading and Unloading at Any Time Order 2021, as detailed in the circulated report and if no objections are received that the proposals be implemented on site as advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
proposed Chain Road, Blaengwrach, Glynneath
– Proposed No Waiting, Loading and Unloading at Any Time Order 2021, as
detailed in the circulated report and if no objections are received that the
proposals be implemented on site as advertised. Reason for Decision: To prevent indiscriminate
parking in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Neath PDF 207 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
Neath Abbey Road and Ffordd Yr
Hen Gaer, Neath – Proposed No Waiting, Loading and
Unloading At Any Time Order 2021, as detailed in the circulated report and if
no objections are received that the proposals be implemented on site as
advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
Neath Abbey Road and Ffordd Yr
Hen Gaer, Neath – Proposed No Waiting, Loading and Unloading
At Any Time Order 2021, as detailed in the circulated report and if no
objections are received that the proposals be implemented on site as
advertised. Reason for Decision: To prevent indiscriminate
parking and assist in traffic flow in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Bryncoch PDF 129 KB Additional documents:
Decision: Having given due regard to the integrated impact assessment that approval be granted to advertise the Main Road, Margaret Street, Bryncoch - Proposed Prohibition of Waiting, Loading or Unloading at Any Time traffic regulation order, as detailed in the circulated report and if no objections are received that the proposals be implemented on site as advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the Main
Road, Margaret Street, Bryncoch - Proposed
Prohibition of Waiting, Loading or Unloading at Any Time traffic regulation
order, as detailed in the circulated report and if no objections are received
that the proposals be implemented on site as advertised. Reason for Decision: To prevent indiscriminate
parking in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Riverside, Neath PDF 130 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise Riverside
(Brickyard Cottages), Neath - Proposed Prohibition of Waiting, Loading or
Unloading at Any Time traffic regulation order and the Proposed Goods Loading Only
traffic regulation order, as detailed in the circulated report and if no
objections are received that the proposals be implemented on site as
advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise
Riverside (Brickyard Cottages), Neath - Proposed Prohibition of Waiting,
Loading or Unloading at Any Time traffic regulation order and the Proposed
Goods Loading Only traffic regulation order, as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Reason for Decision: To prevent indiscriminate
parking and allow Goods Loading only in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Alltwen PDF 207 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that the objection is over ruled to (Gwyn
Street and Heol Phillip, Alltwen,
Pontardawe) (Prohibition of Waiting at Any time) order
2021, as detailed in the circulated report and the scheme be implemented as
advertised and the objector be informed of the decision. Minutes: Decision: Having given due regard to
the integrated impact assessment that the objection is over ruled to (Gwyn
Street and Heol Phillip, Alltwen,
Pontardawe) (Prohibition of Waiting at Any time)
order 2021, as detailed in the circulated report and the scheme be implemented
as advertised and the objector be informed of the decision. Reason for Decision: The proposed scheme will
prevent indiscriminate parking and assist with traffic flow in the interest of
road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Port Talbot PDF 206 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that approval is granted to advertise the
proposed Pen Y Cae and Gwar Y Caeau, Port Talbot – Proposed No Waiting, at Any Time
Order 2021, as detailed in the circulated report and if no objections are
received that the proposals be implemented on site as advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval is granted to advertise the
proposed Pen Y Cae and Gwar Y Caeau,
Port Talbot – Proposed No Waiting, at Any Time Order 2021, as detailed in the
circulated report and if no objections are received that the proposals be
implemented on site as advertised. Reason for Decision: To prevent indiscriminate
parking in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: Tonna PDF 208 KB Additional documents:
Decision: Having given due regard to the
integrated impact assessment approval be granted to advertise the Traffic
Calming Measures at Tonna, Proposed 20 mph speed limits at B4434 Dulais Fach Road, Station Road,.Riverside, Taibanc and
Brunel Close, Tonna traffic regulation order and Proposed B4434 Dulais Fach Road, Tonna –
Proposed speed cushions traffic regulation order as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Minutes: Decision: Having given due regard to the
integrated impact assessment that approval be granted to advertise the Traffic
Calming Measures at Tonna, Proposed 20 mph speed limits at B4434 Dulais Fach Road, Station Road,.Riverside, Taibanc and Brunel Close, Tonna traffic regulation order
and Proposed B4434 Dulais Fach
Road, Tonna – Proposed speed cushions traffic regulation order as detailed in
the circulated report and if no objections are received that the proposals be
implemented on site as advertised. Reason for Decision: To help reduce traffic speed in
the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Traffic Regulation Order/s: A483 Fabian Way PDF 206 KB Additional documents:
Decision: Having had due regard to the
integrated impact that approval be granted to advertise the proposed A483
Fabian Way - Proposed speed limit revisions, as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Minutes: Decision: Having given due regard to
the integrated impact assessment that approval be granted to advertise the
proposed A483 Fabian Way - Proposed speed limit revisions, as detailed in the circulated
report and if no objections are received that the proposals be implemented on
site as advertised. Reason for Decision: The scheme will help to reduce
traffic speed in the interest of road safety. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Prohibition of Waiting at Any Time Order: Tonna PDF 210 KB Additional documents:
Decision: Having given due regard to
the integrated impact assessment that the objections are up held to the
proposed (Henfaes Road and Park Street, Tonna)
(Prohibition of Waiting at Any time) Order 2021, as detailed in the circulated
report and the scheme be withdrawn. The objectors to be informed of the
decision. Minutes: Decision: Having given due regard to
the integrated impact assessment that the objections are up held to the
proposed (Henfaes Road and Park Street, Tonna)
(Prohibition of Waiting at Any time) Order 2021, as detailed in the circulated
report and the scheme be withdrawn and the objectors be informed of the
decision. Reason for Decision: There were no expressions of
support received for the scheme with the majority of those responding objecting
to the proposals. Implementation of
Decision: The decision will be
implemented after the three day call in period. |
|||||||||||||||||||||||||||||||||
Forward Work Programme 2021/2022 PDF 190 KB Minutes: The Forward Work Programme
was noted. |