5 Construction Impact Assessment Summary Report PDF 464 KB
Additional documents:
Decision:
Following
Scrutiny the report was noted.
Minutes:
Peter
Austin gave members an update on the report.
The
focus was on future business case development. City Deal Programme Board had
asked officers to focus on future elements of business case development that
are construction dependent.
Out
of 23 projects, seven have been completed or are about to complete.
There
are two main assessments: 1) likely increase in costs due to inflation and 2)
risk assessment on how cost increases might affect business case delivery.
Previously,
cost assessments were done on a project basis, and the risk/issue assessment at
a Business Case level but now they will include forecasted risks and issues for
future elements at project level as well.
Officers
mentioned Pentre Awel as an example as it has multiple stages which are
flexible in delivery timescale and market dependent. Officers want to ensure
all stakeholders are aware of deliverability.
There
is an anticipated shortfall of £42.6 million for projects yet to be delivered,
these are conservative estimates due to some costs yet to be determined.
Members
were advised that future iterations of the report will provide more detailed
assessments for upcoming projects.
In
terms of risk management, officers are breaking down ‘risks’ and ‘issues’ into
manageable pieces to address them early in the process and the recent
reassessment of risks has led to a reduction in red risks and high amber risks
for completed projects.
There
are no construction cost concerns for the seven completed projects, but a gap
exists for the next set of projects to start being delivered.
Following Scrutiny the report was noted.