Port Talbot Peripheral Distributor Road Phase 2 - Network Rail
Additional documents:
Decision:
That
the terms and conditions provisionally agreed for the acquisition of land and
various rights from Network Rail (as detailed in the private, circulated
report) and payment of professional and legal costs together with payment of
the advance payment of compensation.
Minutes:
Decision:
That
the terms and conditions provisionally agreed for the acquisition of land and
various rights from Network Rail (as detailed in the private, circulated
report) and payment of professional and legal costs together with payment of the
advance payment of compensation, be approved.
Reason for Decision:
To
pay compensation to the affected parties as a result of the Port Talbot
Peripheral Distributor Road, Phase 2 Scheme.
Implementation of Decision:
The
decision will be implemented after the three day call in period.