Decision details

Port Talbot Peripheral Distributor Road Phase 2 - Extension of Statutory period for the Claim from Associated British Ports Holdings Ltd for Compensation

Decision Maker: Regeneration and Sustainable Development Cabinet Board

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decisions:

Decision:

 

That the time limit to negotiate the claim from Associated British Ports Holdings Ltd under Port Talbot PDR Phase 2, be extended to the 30 September, 2019.

 

Reason for Decision:

 

To secure approval for the immediate action required in respect of claims under the Port Talbot peripheral Distributor Road, Phase 2 Scheme.

 

Implementation of Decision:

 

The decision will be implemented after the three day call in period.

Publication date: 07/06/2019

Date of decision: 07/06/2019

Decided at meeting: 07/06/2019 - Regeneration and Sustainable Development Cabinet Board

Effective from: 12/06/2019