Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Following
the proposal of the Environment, Regeneration and Streetscene
Services Scrutiny Committee, held prior to this meeting, Members were supportive
of the addition to the recommendation, as detailed below:
That
having given due regard to the first stage Integrated Impact Assessment:
1. That Option 2 detailed
within the circulated report, be pursued for the foreseeable future, with
palisade fencing to each end of the tunnel being maintained as existing.
2. That a feasibility study for
future use be carried out, and the subsequent options be brought to the Committee
within the next 12 months.
Publication date: 06/10/2022
Date of decision: 06/10/2022
Decided at meeting: 06/10/2022 - Environment, Regeneration and Streetscene Services Cabinet Board