Decision Maker: Streetscene and Engineering Cabinet Board
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Officers
highlighted that they would take into consideration Members concerns.
Decision:
Having
given due regard to the Integrated Impact Assessment, that approval be granted
for officers to commence negotiations and submit a funding application, as detailed
in the private circulated report.
Reason for Decision:
The further development of the proposal will help to alleviate
congestion, help
Air Quality in the locality and release development land in Cimla
presently stymied by capacity issues at this junction.
Implementation of Decision:
The decision will be implemented after the three
day call in period.
Publication date: 02/07/2021
Date of decision: 02/07/2021
Decided at meeting: 02/07/2021 - Streetscene and Engineering Cabinet Board
Effective from: 07/07/2021